F31 West of Minburn Project Update - 8/3/17

Post Date:08/03/2017 4:34 PM

 Manatt's has made good progress with the excavation required for the new pavement.  So far the excavation is complete from the city limits of Minburn to Minburn Court and is continuing to the west.  On Friday, August 4th Manatt's will begin removing and crushing the old pavement.  This process requires that road be totally blocked where the crushing machine is working.  In other words, residents west of the crushing operation will not have access to Minburn via F31.  Any residents west of the crushing operation will need to exit the project by traveling west towards P58 and use the marked detour.  The crushing will be a mobile operation and will begin at the city limits of Minburn and will work towards the west.  A map will be posted to the project website below, and will be updated with an approximate work area as that information becomes available.

Project Website - F31 Paving West of Minburn 

A map of this road closure, and other Dallas County Road Department Projects, can be found at Current Dallas County Road Closures

Click HERE to sign up for eNotifications related to this project.

Questions about this project may be directed to the Dallas County Road Department at 515-993-4289