F31 Project Update 6/28/16

F31/R22 Intersection Closure

Post Date:06/28/2016 4:42 PM

Manatt's has nearly completed the removal and crushing of the existing pavement.  By the end of the day today, all of the pavement will be removed and crushed up to S Avenue.  The remaining portion of pavement between S Avenue and R22 will be removed over the next few days and will require a complete closure of the F31/R22 intersection.  

The intersection will remain closed to through traffic once the pavement removal is complete.

The next stage of construction will be base stabilization and should take about 3 weeks.  During this stage, the road will remain rock and the road will be impassible in the direct vicinity of stabilization activities as they move through the project.

Visit www.dallascountyiowa.gov or click HERE to sign up for eNotifications to receive updates related to this project.

Questions and concerns may be directed to the Dallas County Road Department at 515-993-4289